Projects
February 20, 2022

The Project Structure Plan (WBS)

Project scope planning with the Work Breakdown Structure (WBS). Covers the planning process, structuring principles, design rules, and the top-down approach.

(TU-Munich, 1997). 29 years of experience as a project, program and portfolio manager. Certified as a SAFE Agilist, Project Manager (GPM) and Scrum Master.

The Project Structure Plan (WBS)
Contents

    The project scope planning is part of the project scope management. In this post, we will focus on project scope planning. A core element of project scope planning is the work breakdown structure.

    1. The project scope management

    1.1 Goal of project planning

    Project planning is a central and very important technique of project management. Planning is essential to complete a project successfully.

    Project planning is an important prerequisite for project controlling. The earned values analysis for example requires project planning and a WBS. See our posts:

    • Earned value analysis
    • Earned schedule analysis

    1.2 How to create successfully a project planning?

    A clear and formally approved project order with the desired project scope and project budget is the basis for starting project planning. The project scope includes:

    • Project specific consistent goals
    • Project-specific consistent requirements

    The definition of the project order can be part of the project initiation phase or provided by an internal business department or an external customer.

    To monitor and complete a project successfully a clear project order, entry criteria and a systematically structured planning process are needed.

    1.3 The project charter

    The project has a unique timeline and achieves deliverables following unique requirements and fulfilling unique goals. Therefore the planning process is very crucial as a creative act projecting the planned execution into the future. The basis of precise project planning is the determination of individual goals, which should be SMART (Specific, Measurable, Achievable, Realistic, Time Bound).

    The goals should be already aligned with the most important stakeholders and checked and approved in the context of a clear business case.

    We recommend setting requirements at least on the epic level before beginning the project planning process. The requirements should also be SMART and related to the project goals they meet (traceability requirements to Goals).

    Based on the project goals and main requirements a preliminary estimation leads to an approved budget envelope. The project goals, requirements and budget framework build in general the project charter.

    1.4 The planning process

    Project planning includes according to PMBOK the following primary and secondary planning processes:

    Core Planning Processes:

    • Project scope planning (WBS)
    • Activity planning
    • Resource planning
    • Cost planning
    • Budget planning

    Secondary planning processes:

    • Quality planning
    • Communication planning
    • Risk planning
    • Organizational planning
    • Purchase planning

    2. Project scope planning: WBS

    Project scope management deals with the planning, monitoring and control of the project scope. A core element is the work breakdown structure. All projects require a detailed description of the project work and deliverables.

    Please differentiate between:

    • Product scope: The features and functions that characterize a product, service, or result.
    • Project scope: The work performed to deliver a product, service, or result with the specified features and functions.

    2.1 Definition of WBS

    The Project Management Body of Knowledge defines the work breakdown structure as a hierarchical decomposition of the total scope of work that must be performed by the project team to achieve the project goals and produce the required deliverables.

    As soon as the project charter and scope statement are clearly defined the project manager can start to break down the work. This is the most crucial task to establish a planning baseline for subsequent steps. The work breakdown structure is the most valuable, easiest and most underestimated project management tool.

    A project is generally a complex undertaking and needs to be decomposed into manageable scope sub-components. The result is the work breakdown structure (WBS). The complete WBS is a hierarchical display of all elements of a project scope.

    Through the WBS a project is divided into subtasks and work packages. Hierarchical WBS subtasks are elements that must be further subdivided, work packages are elements at the lowest level.

    The WBS covers the complete project scope. All child WBS elements describe completely the scope of the parent WBS element without overlap.

    2.2 Structuring principles

    • The object-oriented WBS (product-oriented) breaks down the project scope into individual objects that need to be created.
    • The function-oriented WBS considers the functional areas of the project-executing organization.
    • In the phase oriented WBS, these are the project phases at the highest structural level.

    2.3 The top-down approach

    When a project is very large, it is divided into sub-projects. It is recommended to only divide the project into sub WBS elements until the lowest level of the work packages is reached. Each element gets a unique identifier known as the WBS code.

    2.4 The WBS is growing continuously

    At the beginning of the planning process, sufficient information is not always available. WBS tasks in the far future are considered as planning work packages to be detailed later on.

    2.5 Design rules

    The 100% rule states that the WBS includes 100% of the work defined by the project scope and captures all deliverables.

    2.6 Make or Buy

    The WBS must also clearly document which WBS elements are purchased from suppliers and which are developed internally.

    2.7 Plan outcomes/results, not actions

    To make sure that the complete project scope is planned, it is necessary to plan the proposed outcomes or results rather than the activities.

    3. Links

    https://en.wikipedia.org/wiki/Work_breakdown_structure

    Start your free trial and get up to
    35% discount!

    VIP.LEAN ETL for Reporting
    Export all Jira artifacts to any database in real time. Auto-created tables, event-driven updates, and direct BI tool integration with Tableau or Power BI—unlock the full potential of your Jira data.
     
    Start free trial
     
    Get a promotion code
    VIP.LEAN Issue Pickers
    Streamline Jira administration with no-code Issue Picker custom fields powered by JQL. Let users select the right issues in seconds—and automatically create (or update) links for clean, connected Jira data.
     
    Start free trial
     
    Get a promotion code
    VIP.LEAN Behaviours Builder
    Configure dynamic Jira screens with no code, in minutes. Use unlimited conditions across spaces, work types, and fields to tailor the UI.Show/hide, require, lock, relabel, describe, and set/derive values to capture only accurate, relevant data.
     
    Start free trial
     
    Get a promotion code
    VIP.LEAN Create and Link
    Customizable action buttons seamlessly integrated into Jira enable faster issue creation, automatic linking, and dynamic templating—boosting efficiency with powerful Behaviours and Issue Templates.
     
    Start free trial
     
    Get a promotion code